JOR recommendations#
Review recommendations extracted from Jira.
2024-01-30 20:49
Issue key |
Rec# |
Summary |
Report date |
Due Date |
Implementation Status |
Description |
Response |
Implementation Status Description |
---|---|---|---|---|---|---|---|---|
M-III.6-25 |
Hold a risk register scrub/workshop |
JOR_2023_02 |
2023-09-01 |
Implemented |
Hold a dedicated risk register scrub/workshop with subsystem leads and risk owners as well experts in risk management, in addition to the upcoming cost scrub to ensure focus on risk and complete the risk register. This activity should engage all levels of management that will be involved in operations [by September 2023]. |
This was completed in May 2023. The scrub is done and the RDO is updating budgets and Risks. |
A pre-scrub risk workshop was held in April 2023, and served to homogenize and finalize the cost and schedule impact analysis of the risk register, as well as surface some new candidate risks. This workshop was attended by the Risk Board, which includes several internal experts in risk management. |
|
M-III.6-24 |
Develop, document, and socialize detailed decision-making processes |
JOR_2023_02 |
2024-06-01 |
In Progress |
Develop, document, and socialize the detailed decision-making processes for both short-term tactical choices and longer-term strategic operations choices that impact scientific results. This should include the specific lines of communication and decision-making authority within the operations team as well as how feedback is solicited and incorporated from science collaborations and other stakeholders [by one year before operations start]. |
We will do this. A start has been made in rtn-005. |
Authority and responsibility expectations for the Rubin Operations management team have been added to rtn-005. Descriptions of processes for taking in community input an dRubin lines of communication will be added to RDO-018. |
|
M-III.6-23 |
Change management plan and resourcing |
JOR_2023_02 |
2024-03-01 |
In Progress |
Ensure that sufficient resourcing is allocated during the pre-operations phase to allow all future operations staff to become engaged, regardless of their ongoing construction activities [by March 2024]. This includes but is not limited to: • Develop a plan to transition the existing internal project Science Team to operations, including detailing the processes for this group within the operations plan. • Continue work to solidify the processes that allow delegating responsibility to lower-level managers and enabling them to make appropriate decisions. • Deliver the change management plan that is understood and accepted by all staff with high priority. |
We will do the first two bullets. It is not clear we need a change management plan so much as a transition activities that includes regular communication down to the individual team member, clarity and sign off on individual roles and responsibilities, etc. |
Work is being scheduled on this for FY24 Q1 and Q2. |
|
M-III.6-22 |
Best hiring practices for all Rubin hiring committees |
JOR_2023_02 |
2024-03-01 |
In Progress |
Complete and implement a set of best hiring practices for all Rubin hiring committees, regardless of parent organization for the hire, that includes within it best practices to ensure diversity, equity, and inclusion [by March 2024]. |
We will do this. |
Work on a Rubin Hiring Toolkit that addresses this recommendation has been scheduled for FY24 Q1 and Q2. |
|
M-III.6-21 |
Formalize advisory committee processes |
JOR_2023_02 |
2024-03-01 |
In Progress |
Formalize the make-up and meeting cadence of the advisory committees, particularly for the case of the science collaborations, to ensure the science collaborations are appropriately represented and that the process for acknowledging and responding to their advice is clear. Additionally, create a single unified organization chart that shows all advisory committees and the communication lines to management [by March 2024]. |
We will do this. Most of it already is documented in RDO-018. |
Work is being scheduled to update RDO-018, the Rubin Operations Plan, in FY24 Q1 and Q2 prior to the next review. |
|
M-III.6-20 |
Develop salary equity process for AURA & SLAC |
JOR_2023_02 |
2024-03-01 |
In Progress |
Develop a process to ensure AURA and SLAC review salary and benefits at least annually to ensure similar compensation for similar positions and experience across the organizations [by March 2024]. |
This will depend on AURA and SLAC HR. |
Work on this is scheduled for FY24 Q1 and Q2. |
|
M-III.6-19 |
Policy to allow employees to work from any state |
JOR_2023_02 |
2024-02-01 |
In Progress |
Make a policy change at AURA allowing for the hiring of employees to work in any state, without consideration for AURA’s existing presence in that state [by the next review]. |
Rubin will work with NOIRLab leadership to enable this change with AURA HQ. Rubin has already worked with NOIRLab to put in a formal request to add Oregon, NY, and North Carolina. This request is in AURAs hands. |
As of end December, 2023, AURA is still working on registering Oregon. Rubin noted an ongoing search for software engineering that had highly qualified candidates from Massachusetts and Missouri to NOIRLab leadership. These recruits might be possible to hire via SLAC. |
|
ESH-III.5-18 |
Lessons learned folded into ops |
JOR_2023_02 |
2023-06-01 |
Implemented |
Ensure that the lessons learned and recommendations from construction are folded into operations. • Complete the Winter Operations Plan and Response to Weather Emergency Situations plan well in advance of the 2023 winter season to allow time for equipment procurement, dry run exercises, testing of equipment [by June 2023]. • Develop a Fatigue Mitigation Plan. Suggest including fatigue observation checklists and assessments [by June 2023]. • Perform an annually quantitative measure of the impact of implementing recommendations from the external traffic safety company evaluation. [Complete the first one prior to the next operations review.] |
Winter plan 2023 on place Fatigue Mitigation program on progress Safety Road Enginnerering Study (done) Corrective Measures in progress |
Winter plan 2023 on place Fatigue Mitigation program on progress Safety Road Enginnerering Study (done) Corrective Measures in progress |
|
ESH-III.5-17 |
Document lessons learned |
JOR_2023_02 |
2023-06-01 |
Implemented |
Document the lessons learned recovering from a major setback such as resuming work after 2 months of shutdown following the incident that took place at SLAC in December 2022 and share with the Rubin team [by June 2023]. |
Safety Lesson Learned has been distributed |
||
ESH-III.5-16 |
Plan to execute recommendations |
JOR_2023_02 |
2023-09-01 |
Implemented |
Create a plan for executing the recommendations from the ES&H review of the Rubin Observatory which took place on 10/6/22. Focus on electrical safety, confined spaces, ladder safety/working at heights and earthquake bracing [by September 2023]. |
Reinforce of : Electrical Safety ; LOTO training update Confined Sapce : Develop of a Confine Space Training Working on height and Fall protecction : review of current traning and add of ladder safety |
[https://docushare.lsst.org/docushare/dsweb/G]et/Document-40659/Safety%20Orientation%202023eng.pdf |
|
ESH-III.5-15 |
Implementation of Road Safety Study |
JOR_2023_02 |
2023-07-01 |
Implemented |
Deliver a timeline for implementing the recommendations from the Road Safety Study (Estudio de Seguridad Vial by Ambitrans Ingenieros Consultadores, SpA) report [by July 2023]. |
Minimun Commuting Time Test , March 2023 , done , Submit new Minimum Timing Table to AURA-O and RSLT (done) GPS monitoring Submitted to AURA-O for approval (May 2023) Distribution of new Minumum time comutting , June 2023 |
||
CS-III.4-14 |
Training on new tools |
JOR_2023_02 |
2024-01-31 |
In Progress |
Provide sufficient training on new tools and budget and the budget planning process for ADs and team leads [prior to the launch of next annual planning cycle]. |
We will train the ADs on all the tools necessary to do their part of planning and tracking. |
The Rubin Directorate held a briefing on the FY23 scrub outcome and reviewed the staffing tools as they are deployed during the scrub by the Team leads. The briefing was attended by team leads for ROO, RDM, RPF, REO and RDO. Briefing slides are here. Notes and feedback/Q&A were captured in the private Confluence pages of the RDO OPS Exec. This training completes the JOR23 recommendation, but training will continue through each scrub cycle. |
|
CS-III.4-13 |
Consolidated report Plan vs Actual |
JOR_2023_02 |
2023-08-31 |
In Progress |
Develop a consolidated report showing plan versus actuals by WBS by month for the Rubin Operations team and agencies [by summer 2023]. |
We will make this report. The NSF side is essentially already done in collaboration with Program Operations and NOIRLab Management Services. |
Here is the working epic https://jira.lsstcorp.org/browse/PREOPS-4152 |
|
SP-III.3-12 |
Track RSP usage |
JOR_2023_02 |
2024-06-28 |
Not Started |
Continue to find ways to track how broadly the Rubin data and RSP are being used by the community. In particular, assess the impact of the LSST survey data reaching historically underrepresented groups [before Data Preview 1]. |
The RPF Community Science team will investigate ways to track RSP usage |
The Community Science Team of the Rubin System Performance Department are making plans on how to carry out these assessments and track the usage. Results would be reported in the annual report. |
|
SP-III.3-11 |
Visibility of change procedures for the survey cadence, scheduling and strategy |
JOR_2023_02 |
2024-02-29 |
Not Started |
Increase the visibility of the change procedures of the survey cadence, scheduling, and strategy to inform the community and agencies regarding ongoing compliance with the SRD [by September 2023]. |
A process will be developed to make the change procedures of the survey cadence, scheduling, and strategy more visible and inform the community and agencies regarding ongoing compliance with the SRD. |
We have a documentation site set up but it is down at the moment. More content needs to be added. |
|
SP-III.3-10 |
Add a formal review and sign off following pilot processing runs |
JOR_2023_02 |
2024-02-01 |
Not Started |
Add a formal review and sign off for the transition to data release processing. The signoff should occur between the end of the pilot run processing and the start of production processing [before the next review]. |
A formal review and sign off following pilot processing runs will be added |
This work is being planned. |
|
SP-III.3-9 |
Mitigate system engineering work overload |
JOR_2023_02 |
2023-12-31 |
In Progress |
Mitigate the upcoming system engineering work overload in the handoff between Rubin construction and RPF operations. One possible mitigation is the use of external contractors [by the end of 2023]. |
Consulting help will be hired to mitigate system engineering work overload |
The System Performance Department is putting together a Statement of Work which would go to AURA CAS to start a procurement and contract for service to help alleviate some of this overload. |
|
SP-III.3-8 |
Implementation of the Operations CCB |
JOR_2023_02 |
2023-12-31 |
Not Started |
Complete the implementation of the RPF CCB and RB [by the end of 2023]. |
The Operations CCB will be implemented by the RPF Systems Engineering team. The Systems Engineering team has few resources to dedicate to pre-operations work so consulting help will be needed |
The Director’s office and System Performance have had discussions on moving this forward. |
|
DM-III.2-7 |
Metric of success |
JOR_2023_02 |
2024-06-28 |
Not Started |
Define a metric of success that enables the RDM team to evaluate their chosen user support model, and the efficacy of the community support [by Data Preview 1]. |
One or more metrics of success will be defined to enable evaluation of the chosen user support model, and the efficacy of the community support |
The System Performance Team will address this Review Recommendations as the User Model falls in RPF and not Data Management. The work is somewhat related to recommendation DM-III.2-6 which is in progress. No significant progress update for this particular recommendation at this time. |
|
DM-III.2-6 |
Concise and complete set of performance metrics |
JOR_2023_02 |
2024-06-28 |
In Progress |
Develop and agree on a concise and complete set of performance metrics that are tracked by the team and reported to operations management [by Data Preview 1]. |
We do need to document a set of (non science science) performance metrics - it has not been done yet. |
Work has begun to document a set of (non science science) performance metrics. Data Management and System Performance will work jointly on this. |
|
DM-III.2-5 |
Agreement with SLAC |
JOR_2023_02 |
2023-06-01 |
Implemented |
Re-evaluate the agreement with SLAC offering new personnel software staff positions and consider instead continuing existing software staff that could transition from the NSF construction project [by June 2023]. |
The FY24 Scrub allowed us to explore this topic and make some advances. SLAC has been working with us to retain more staff from construction. It not obvious we can re-valuate the agreement with SLAC, DOE need to fund half the project. We will keep pressing our case. |
The FY24 Scrub allowed us to explore this topic and make some advances. SLAC has been working with us to retain more staff from construction. Directors office is satisfied with the progress made and approves this recommendation for closure. |
|
DM-III.2-4 |
Decision to split software developement |
JOR_2023_02 |
2024-02-01 |
In Progress |
Re-evaluate the decision to split software developer management between different departments [by the next operations review]. |
We will convene a discussion among the ADs to see how to best move forward. |
We will convene a discussion among the ADs to see how to best move forward. |
|
OO-III.1-3 |
Plan for SLAC maintenance |
JOR_2023_02 |
2023-10-01 |
In Progress |
Ensure that the plan for SLAC maintenance of the LSSTcam is fully described for future reviews [by FY 2024]. |
Both the construction and operations teams (they are essentially one in the same) continue to work closely with the team at SLAC developing LSSTCam. Maintenance plans are continually being updated as specific details are learned during the final test and verification action phase for the instrument. These details are being folded into the Rubin Observatory Operations (ROO) strategic maintenance plan and include reassessment of both technical and personnel resource needed to maintain LSSTCam through the 10-year LSST program. The ROO Strategic Maintenance PLan do men tis a key deliverable for FY23 and will be a featured discussion point in subsequent reviews. |
Blum and Marshall met with Camera team in November at SLAC to discuss maintenance and OPS supports needs. Claver visited SLAC the following week to follow up and further advance planning. |
|
OO-III.1-2 |
Re-consider the on-site presence |
JOR_2023_02 |
2023-10-01 |
Not Started |
Re-consider the on-site presence of engineering and technical support staff during nighttime for the first years of operations, until steady-state operation with nominal unplanned downtime has been reached [by FY 2024]. |
As the construction project progresses through its commissioning phase it is clearly evident that significant technical presence will be needed in the early stages of operations. The Rubin Observatory Operations (ROO) plan as presented is for steady state with a minimal technical presence needed at the summit. We have always planned that there would be a transition period between the end of construction and steady state operations. The details of the needed technical staff during nighttime operations is becoming clearer as the construction commissioning advance. Adjustment are currently being made in the detailed transition plan for nighttime support. With the need for Technicalical support in mind we are also training up the nighttime Observing Specialists to have some level of technical awareness and expertise to serve as the front line for diagnosis and solving technical issues as they arise. This is a core part of the Observing Specialists functions and has been part of the plan from the beginning. The technical training of the Observing Specialists is part of the designed work scope during construction commissioning. |
This has been reconsidered and it is acknowledged that experience gained from the current commissioning phase of the Construction project is informing Operations on night time support that will be needed initially in operations until steady state. |
|
OO-III.1-1 |
Monitor the effectiveness of the initial maintenance strategy |
JOR_2023_02 |
2023-10-01 |
Not Started |
Monitor the effectiveness of the initial maintenance strategy during the first 2 years of operation and adjust the strategy accordingly if needed. Reserve corresponding resources in the operations plan [by FY 2024]. |
As part of the Rubin Construction integration, test and commissioning effort the Rubin Observatory Operations (ROO) team its carefully monitoring the maintenance needs of the observatory. As systems are being integrated and tested the ROO team as part of their construction/operations dual responsibilities are documenting technical issues and noting specific maintenance needs. These will be recorded in the Computerized Maintenance Management System (CMMS) under development by the construction project. This body of information is currently being used to update the maintenance strategy and planning with resultant resources needed on various timescales. The ROO Strategic Maintenance Plan is a key deliverable from the FY23 early operations efforts. This document is being developed now with contributions from the ROO Team and Group leads (who are also part of the Rubin construction team). Staffing and non-labor resource adjustments are expected from the Maintenance Strategic Plan update and will be part of revised operations planning for ROO in FY24. |
This has been started and findings are being recorded in the CMMS |